Finally the pladur guy showed up again and finished the ceiling of the live and control room. It still needs to fill in the joints.
The roof is finished and joints painted with a rubber ink to be sure no water comes in.
Toillet back wall is ready and looking good
In addition the water deposit for the toillet arrived and was installed yesterday
Plumbing for all the toillet and AC drain is complete.
Electrical Box wall is filled with concrete and finished.
Playing a bit with the panorama feature of my smartphone in the live room