Been a while since the last update so here are a load of new pictures.
Here is a detail of the ventilation to inflate fresh air into the live room and vocal booth
This is an image of the attenuator to the vocal booth.
The AC units have arrived and are waiting assembly.
Meanwhile the sewer is connected to the main sewer pipe and a hatch has been built to provide access both near the toillet area and in the spot where it joins the main sewer pipe
The glass for the control room window has arrived. These things are huge. I took a picture with a 2 Eur coin for scale.
After the ventilation is installed they built a hatch to provide access to the motor the inflates the air. The hallway and corridor ceilings are finished and ready for painting.
Now that the weather has changed and there is 30º outside the cements are drying inside and a considerable quantity of humidity is being generated inside. I had to put a de-humidifier as it was reaching 90% humidity.